At 54.7 gw, Wind capacity may fall short of target

Written By DNA Money Correspondent | Updated: Apr 29, 2019, 05:20 AM IST

175 gw - total renewable energy capacity target by 2022

Land acquisition issues and grid bottlenecks have been leading to delays in project implementation in the sector, Fitch Solutions Macro Research has said in a report

54.7 gw – India to install wind capacity by 2022

60 gw – wind capacity target set by the govt

175 gw – total renewable energy capacity target by 2022

100 gw – solar capacity target

4.5 gw – average wind capacity between 2019 and 2022

20 gw – govt seeks to tender wind capacity by March 2020

The combination of several challenges in the country's wind power sector will hit near-term growth momentum, including land availability hurdles, grid access bottlenecks and concerns over the viability of low tender bids," 
— The report said