Get slums out of the way: Mumbai International Airport Limited

Written By Surendra Gangan | Updated:

Says unless 80,000 families are moved elsewhere, airport modernisation may not kick off

The Mumbai International Airport Limited (MIAL), which has been appointed to carry out the modernisation of the Mumbai airport, recently warned the state government that unless rehabilitation of slumdwellers takes off, plans of modernisation may stay that away.

In a presentation made by MIAL two weeks ago to chief minister Prithviraj Chavan, the company brought to the notice of the government that slums are coming in the way of modernisation, especially work on the new international terminal and the elevated access road from the expressway to the terminal, and pressed for the immediate commencement of the slum rehabilitation programme.

But that’s easier said than done. Although nearly 80,000 families need to be rehabilitated, land for just about 18,000 houses is currently available.

The Housing Development and Infrastructure Limited (HDIL), which has been entrusted with the task of constructing rehabilitation tenements, claims to have completed 85% of the 18,000 houses at Kurla as part phase-one of the slum rehabilitation project. But, government sources tell a different tale: not only is phase-one running much behind schedule, but government authorities have also failed to complete within the stipulated time a survey of families eligible to get houses.

The MIAL had asked two plots — owned by University of Mumbai and the Brihanmumbai Municipal Corporation — to rehabilitate 68,000 more families, but the government turned down the demand.

On the other hand, the allotment of tenements ready for possession could not be initiated as the survey of tenants is inching at a snail’s pace. The suburban collector has surveyed only 10,909 families, of which only 3,116 are reportedly eligible as per norms of the Slum Rehabilitation Authority.

“The survey work has been slowed down due to some technical difficulty. Unless the survey is completed, we cannot allot the tenements to slumdwellers,” said Nirmalkumar Deshmukh, suburban collector.

The HDIL’s spokesperson refused to comment.

According to the original plan, the rehabilitation of all 85,000 families had to be completed by mid-2014. the first phase was supposed to be completed by late 2010.

But going by the current pace of work and constraints on land availability, the rehabilitation is expected to be delayed further. Dominoes’ effect: the modernisation work of the international airport is bound to be affected.